00:00 q1. A works twice as fast as
b. If b can complete a work in 12 days in dependently, the number of days in which a and b together finish the work is?
Answers
Answered by
1
12 MULTIPLY 2 (TWICE)
=24
24+12
=36
ANS)THEY BOTH CAN COMPLETE IT IN 36 DAYS.