Math, asked by snamdas735gmailcom, 10 months ago

05. A can complete a work in 24 days. If B works twice as fast as A, in how many days
they together will complete the work?
(a) 5 days (b) 6 days
(c) 8 days (d) 9 days.​

Answers

Answered by sumendraxyz
2

A take 24 days

B take fast than twice of A =24/2 =12 days.

both takes,

(24/12)+(12/2) =2+6 =8 days

Similar questions