1/2 part of ram sham's work takes 1/6 part time.ram and sham both do it toghter in 10 days.how many days sham alone done?
Answers
Answered by
0
Answer:
Step-by-step explanation:
for half work ram takes 1/6 time of shyam
for total work ram takes= 1/3 time
let assume that for total work ram takes =1x day
shyam can take= 3x day
so there work ratio will be ram:shyam= 3:1
they together can take 10 days ⇒ for 1 day ram can do 3 units and shyam 1 unit
for 10 days they both together= 10×(3+1)=40 units
now in how many days sham alone can complete 40 units=
total work/1 day work
=40/1=40 days
hope you understand