Math, asked by ripusingh0189, 22 hours ago

1. 20 men and 25 women together can complete a work in 5 days. It takes 150 days for one man
alone to complete the work. How many days will be required for one woman to complete the
same work?

A) 300 B) 325 C) 350 D) 375​

Answers

Answered by kamalrajatjoshi94
14

Answer:

According to question:-

5(20M+25W)=1M×150

100M+125W=150M

125W=150M-100M

125W=50M

5W=2M

1 men can do the work in 150 days.

2 men can do the work in 150/2 =75 days.

No. of days by women=75×5

=375 days.

Hence , option d is correct.

Answered by amitnrw
2

Given : 20 men and 25 women together can complete a work in 5 days.

It takes 150 days for one man alone to complete the work.

To Find :  How many days will be required for one woman to complete the

same work?

Solution:

20 men and 25 women together can complete a work in 5 days.

=> Total work = 20 * 5  man days + 25* 5 woman days

= 100 Man days + 125 woman days

It takes 150 days for one man alone to complete the work.

=> Total Work  = 150 Man days

100 Man days + 125 woman days = 150 Man days

=>  125 woman days = 50 Man days

Multiplying by 3 both sides

=>  375 woman days = 150 Man days

Total Work  = 150 Man days = 375 woman days

Hence 375 days will be required for one woman to complete the

same work

Learn More:

20 men can complete a piece of work in 15 days. One man starts the ...

brainly.in/question/9066294

A work is completed such that on the nth day from the start n men ...

brainly.in/question/11508647

Similar questions