1. 3/4 ठेका पूर्ण हुआ। प्रमाणित कार्य, ठेका मूल्य का 1/2 है। 3/4 कार्य की लागत 3,00,000 ₹ है। अप्रमाणित कार्य की
लागत की गणना कीजिये।
Contract completed is 3/4. Work certified is 1/2 of Contract price. Cost of 3/4 work is ₹3,00,000,
Calculate cost of work uncertified.
Answers
Answered by
0
Answer:
one by one question bhejo
3,00000000000