1. 6 men can complete the electric fitting in a building in 7 days. How many days will it take 21 mento
the job?
Answers
Answered by
2
Answer:
Step-by-step explanation:
Number of days required by 6 men to complete the work = 7
Number of days required by 1 man to complete the work = 7 × 6
Number of days required by 21 men to complete the work = 42/21 = 2
Hence, 2 days is required by 21 men to complete the work.
HOPE THIS HELPS !
Answered by
0
Answer:
2 days.
Step-by-Step Explanation:
→ 6 men can complete the electric fitting in a building in 7 days. So,
→ 21 men can do the job in days. So,
We get,
If the number of men will increase, So, the number of days for the job will decrease. Hence, here is inverse proportion.
Since in inversely proportional term, where x and y has two variations,
Where, k is a constant term.
Here,
x :-
y :-
Therefore,
Hence, 21 men can do that job in 2 days.
Similar questions
Physics,
2 months ago
India Languages,
2 months ago
Math,
2 months ago
Math,
6 months ago
English,
10 months ago
Environmental Sciences,
10 months ago