Math, asked by vamsisampathcdm, 8 months ago

1. A, B and C together can complete a piece of work in 10
days. All the three started working at it together and after
4 days A left. Then B and C together completed the work
in 10 more days. A lone could complete the work in
(a) 15 days (b) 16 days(c) 25 days (d) 50 days​

Answers

Answered by vikash201097
1

Answer:

25 days

Step-by-step explanation:

(A+B+C) do 1 work in 10 days.

(A+B+C)'s 1 day work = 1/10

They work together for 4 days.

∴Workdone by them in 4 days=4/10

= 2/5

Remaining work = 1 - 2/5

= 3/5

(B+C) take 10 more days to complete 3/5 work.

So (B+C)'s 1 day work = 3/50

Now A'S 1 day work

=(A+B+C)'s 1 day work - (B+C)'s 1 day work

=1/10- 3/50

= 1/25

A does 125 work in 1 day

A alone could complete the work in 25days

Similar questions