1. A can d 3/4 of the work in 12 days. In how many days can he complete 1/8 th of the work?

No spamm और else I will report. ​

Answers

Answered by isthatJhnvy
6

Answer:

Answer:If the person completes 3/4 or 75 % of the work content in 12 days he is on schedule to complete 100% in 16 days1/8 of 16 days work content is therefore 2 days Answer is 1/8 of the entire job is 2 days.

Answered by patnaikswapnasree2
26

Answer:

A can do 3/4 work in 12 days

A can do 1 work in =12/3/4=16

A can do work in 1/8= 1/8× 16 = 2

Therefore, A can do the work in 2 days