1 A can do a certain work in the same time in
which B and C together can do it. If A and B
together could do it in 10 days and C alone in 50
days, then B alone could do the work in
1. 15 days 2. 20 days 3. 25 days 4. 30 days
Answers
Answer:
If A completes the work in n days as such by anology B & C together complete the work in same time
Now efficiency of A = 1/n th part of work per day
Combined efficiency of B & C = efficiency of A
E(A) + E(B) + E(C) = 1/n + 1/n = 2/n
Efficiency of A & B = 1/10
Efficiency of C = 1/50
We can write as
E(A) + E(B) +E(C) = 1/10 + 1/50
6/50 = 2/n
n = 100/6
Since E(A) + E(B) = 1/10
E(A) = 6/100
E(B) = 1/10 -6/100 = 4/100 = 1/25
Therefore B will complete the work alone in 25 days
Step-by-step explanation:
HOPE IT WILL HELP YOU
I TRIED
I GUESS IT IS CORRECT
Given :
- ( A + B ) = 10 days
- C = 50 days
According to the question :
Let,
( A + B )'s 1 day work = 1 / 10
C's 1 day work = 1 / 50
☞ ( A + B + C )'s 1 day work ,
=> 1 / 10 + 1 / 50 [ LCM = 50 ]
=> 6 / 50
=> 3 / 25
- A's 1 day work = ( B + C )'s 1 day work [ given ]
Let the work be ' x '
=> 2x ( A's 1 day work ) = 3 / 25
=> A's 1 day work = 3 / 25 × 2
=> A's 1 day work = 3 / 50
To find :
B's 1 day work = ( A + B )'s day - A's 1 day work
=> 1 / 10 - 3 / 50 [ LCM = 50 ]
=> 2 / 50
=> 1 / 25