1. A can do a piece of work in 10 days, B can do the same work in 20 days, with the help
of C, they finished the work in 4 days. In how many days C can do the work in alone
Answers
Answered by
0
Answer:
C can do the work alone in 10 days
Step-by-step explanation:
for convenience we divide the piece of work in 20 parts
According to this,
A's rate of doing work = 2 parts/day
B's rate of doing work = 1 part/day
Let C's rate of doing work = x parts/day
All of them finished the work in 4 days
so the combined rate of doing work = 20 parts / 4 days
= 5 parts/day
combined rate = A' rate + B's rate + C's rate
5 = 2 + 1 + x
x= 2 parts/day
time taken by c to finish the work alone= 20 parts / 2 parts/day
= 10 days