1. A can do a piece of work in 12 days, B can do the same work in 8 days, and C can do the same job in th time required by both A and B. If both A and B work together for 3 days, then C completes the job. In how many days C finished the work?
Answers
Answered by
151
To solve this question at first we have find the work done by A and B in how many days but A and didn't complete the job . Rest Job done by C. As we know that work is assumed by 1 .
- A+B work only 3 day's
- Rest work done be C:-
- Now work done by C:-
Answered by
60
Given :-
A can do a piece of work in 12 days, B can do the same work in 8 days, and C can do the same job in th time required by both A and B. If both A and B work together for 3 days,
To Find :-
In how many days C finished the work?
Solution :-
A can do in 12 days
One day work of A = 1/12
B can do in 8 days
One day work of B = 1/8
C can do in time required by both A and B
A and B can do in 3 days
Now
(1/12 + 1/8) × 3
(2 + 3/24) × 3
5/24 × 3
5/8
Now
The remaining job
(1 - 5/8)
(8 - 5/8)
3/8
Now
Days required for C
5/24 × 3/8
5/8 × 1/8
5/64
Now
Days taken by C = 64
Similar questions