1. A can do a piece of work in 3 days, B can do it in 6 days. How long will A and B take to complete
the work working together?
Answers
Answered by
0
Answer:
2 days
Step-by-step explanation:
hope it helps you. . . . . . . . . . .
Answered by
1
Answer:
We will solve this using the LCM technique.
A takes 3 days & B takes 6 days. So, let the total work be LCM(3,6) = 6 Units
A -> 3 days = 4 Units/day
B -> 6 days = 3 Units/day
A + B = 7 Units/day
Thus, TOTAL TIME = 247 = 3 37 Days (Answer)