1) A contract on construction job specifies a penalty for delay of completion beyond a
certain date as follows: ` 200 for the first day, ` 250 for the second day, ` 300 for the third
day, etc., the penalty for each succeeding day being ` 50 more than for the preceding day.
How much money the contractor has to pay as penalty, if he has delayed the work by 30
days?
Answers
Answered by
5
Answer:
First generate a series 200+250+300+350+....
Step-by-step explanation:
And now applying the of Arithmetic Progression, find out the sum of first 30 terms.
And it's the required answer.
I didn't solve it here, so that you get the process.
Thanks.
Similar questions