1.A contractor undertakes to dig a canal, 6 kilometres long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of canal have been completed. How many more men must be employed to finish the work in time?

Answers

Answered by mohammadmoinpasha747
2

Answer:

110 mens

Step-by-step explanation:

110 men's can be employed

Answered by stelladaniel216
4

Answer:

Please refer the picture attached to this answer for the solution.

Step-by-step explanation:

The step-by-step solution is illustrated to the picture attached to this answer.