1.A contractor undertakes to dig a canal, 6 kilometres long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of canal have been completed. How many more men must be employed to finish the work in time?
Answers
Answered by
2
Answer:
110 mens
Step-by-step explanation:
110 men's can be employed
Answered by
4
Answer:
Please refer the picture attached to this answer for the solution.
Step-by-step explanation:
The step-by-step solution is illustrated to the picture attached to this answer.
Attachments:
Similar questions