Accountancy, asked by aratikumari43953, 1 month ago

1. A work measurement study was carried out in a firm for 8 hours and the following information was available : Units produced 40 ; Performance rating 80%; Idle time 10% ; Allowance time 10% of standard time. What is standard time for task ? ​

Answers

Answered by priyanka3415
6

Answer:

9.5 min

why ?

8hours (given)

8×60 min = 480 min

less: idle time 10% of 480 = 48

now less 480-48= 432 ( actual time labour took)

time per unit = 432/40 ( as 40 is given as number of units produced)

= 10.8 min

performance rate =80%

therefore performance rate per unit would be

10.8×80/100 = 8.64 min

now add allowance time = 8.64 × 10/100= .864

so standard time = 8.64+ .864 = 9.504 min