1 An employer has a workforce of 300
employees to finish a project in 8 months.
How many extra employees should be
employ to complete the project in 6
months?
Answers
Answered by
6
Answer:
hi
Step-by-step explanation:
100 extra employees will be required to complete the project in 6 months.
Explanation:
We are given that:
Workforce = 300 employees
The time period to finish project = 8 months
To Find: Number of extra employees = ?
Solution:
300 employees 8 months 1 project
300 employees 1 month 1 / 8 project
1 employee 1 month (1/8) x 1/300
x employee 6 month [1/ 8 x 300] x 6 ] x x = 1
1 x 6x / 8 x 300 = 1
x = 8 x 50 = 400 employee
400 - 300 = 100 employee
Thus 100 employees will be required to complete the project in 6 months.