1. If 12 men or 18 women can complete a piece
of work in 7 days, in how many days can 4 men
and 8 women complete the same work?
Answers
Answered by
2
Answer:
They will complete work in 9 days
Step-by-step explanation:
Consider,
- m = unit work done by men per day.
- w = unit work done by women per day.
Then unitary method ,
12m × 7 = 18w × 7 {same work}
⇒ 84m = 126w
⇒ m/w =2/3 {efficacy of men and women to complete a work in a day}
Total work which to complete is 12×2×7.
Time taken by 8 men and 16 women is = total work/their per day work
So,
12×2×7/(4×2+8×3)
⇒ (36×14)/(56)
⇒ 504/56
⇒ 9 days
They will complete work in 9 days.