1. If 18 men working 5 hours a day for 8 days can complete a job, how many men working 8
hours a day for 6 days will be needed?
a) 10 men b) 7 men
c) 15 men
d) 20 men
Answers
Answered by
1
Answer:
15 Men
Step-by-step explanation:
If 18 men working 5 hours a day for 8 days can complete a job
Then Total man hour per day
= No of Man *Working hrs
=18*5=90 man hour
Total man hour in 8 days=90*8=720 man hour
Now given
No of men=x, days=6,hours=8
So x*6*8=720
x=720/48=15 men