1) If P and Q together can complete a job in 3 days while
P alone can do the same in 12 days, then how many days
would be required by Q to do the job alone?
Answers
Answered by
1
Answer:
q can also do in 12 days answer is 12
Answered by
0
Answer:
24(I think not so sure please tell whats the correct one)