1. Peter can do a piece of work in 12 days. Mihir is found to be 50% more efficient than Peter.
If Mihir is given the piece of work, how long will he take to do it?​

Answers

Answered by dwivedisk1995
1

Answer:

18

Step-by-step explanation:

12 work day for peter.

it means in one day 12 unit of work is done by peter.

Mihir is more efficient so in one day ,he will do 1.5*12 unit of work means 18 unit of work...

so 18 work day for mihir..

so it means 18 days .....

thankyou.

hope it will work.

follow and support.