15 व्यक्ति किसी काम को 25 दिन में कर सकते हैं उससे दुगना काम 10 व्यक्ति कितने दिन में करेंगे​

Answers

Answered by letslearnmaths40
2

Step-by-step explanation:

work done by 1 man = 25×15 = 375 days

work done by 10 man = 375÷10 = 37.5 days

Double work = 37.5×2 = 75 days