1. To do a certain work, A and B work on alternate days,
with B beginning the work on the first day. A can fin-
ish the work alone in 48 days. If the work gets com-
pleted in 11 days, then B alone can finish 4 times
the same work in?
Answers
Answered by
1
B does 4 times of the work in 27 days
Step-by-step explanation:
A and B worked for 16/3 and 6 days
A' s one day work = 1/48
As 16/3 days work = 1/9
1 = 1/9 + 6/days taken by B to complete the work alone
So, here days taken by B to complete the work alone = a
8/9 = 6/a
a = 27/4
Therefore,
Days to complete the 4 times of that work = 4 x 27/4 = 27 days
Hence, B does 4 times of the work in 27 days.