10.
8 men and 6 boys can do a work in 25 days and
10 men and 15 boys can do that work in 16
days. How long will 1 man and 1 boy take to do
the work ?
Answers
Answered by
3
Answer:
48 days is the answer for the question
Answered by
7
Step-by-step explanation:
48 days is the answer.
please mark me the brainliest