10. A can do 2/3 of a certain work in 16 days and B can do
1/4
of the same work in 3 days. In how
many days can both finish the work, working together?
Answers
Answered by
1
Answer:
8 days is the answer to ur question.
For procedure viewthe above pic.
Step-by-step explanation:
HOPE THIS WILL HELP YOU:)