Math, asked by sadhanasingh8585, 1 year ago


10. A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the
remaining work in 42 days. In how many days could both do i

Answers

Answered by Tamilneyan
5

Answer:

A and B together completes the work in = 30 days

Step-by-step explanation: