10. Anil will take 10 days to dig a well. Sunil will take 15 days to dig the same well. In how many days will
they be able to dig the well if they work together?
Answers
Answered by
2
hi friend,
here is your answer
please follow me
Answer:
6 days
In 6 days Anil and Sunil are able to dig the well if they work together
hope it helps you and you understood
if helps please follow me
Attachments:
Answered by
6
6days
Step-by-step explanation:
anil one day work=1/10
Sunil one day work=1/15
both one day work is=1/10+1/15
=5/30
=1/6
both complete work together=1÷1/6 days
=1×6/1=6days