10 boys can dig a pitch in 15 hours. how long will 8 boys take to do it?
Answers
Answered by
0
Answer:
18 6/8 hours
Step-by-step explanation:
10 boys 15 hours
1 boy. 15×10 hours
8 boys. 15×10/8
=18 6/8hours
Answered by
0
Answer:
75 Hours is the answer. The attachment will tell you the complete method of working out.
Attachments: