Math, asked by sweetlinecrysolite, 7 months ago

10 farmers can plough a field in 21 days . Find the number of days reduced if 14 farmers ploughed the same field​

Answers

Answered by Anonymous
6

6 days

Step-by-step explanation:

Given : 10 farmer can plough a field in 20 days

To Find: How many days lesser will 14 farmers take to plough the same field

Solution:

10 farmer can plough a field in 20 days

1 farmer can plough a field in days = 20 \times 1020×10

14 farmer can plough a field in days = 20×10/14

= 14.28

Lesser days will 14 farmers take to plough the same field = 20 -14.28 = 5.72

So, it will takes approximately 6 days lesser for 14 farmers to plough the same field

Hope it helps uh....

Answered by Anonymous
0

Answer:

Mark upper ans as brainliest

Similar questions