10. If 72 workers can do a piece of work in 40 days, in how many days will 64 workers complete the same work
(first right answer will get Barnliest)
Answers
Answered by
5
Answer:
45 days
Step-by-step explanation:
64 workers complete the work within=40×72/64=45 days answer.