10. If 72 workers can do a piece of work in 40 days, in how many days will 64 workers complete the same work
(first right answer will get Barnliest)​

Answers

Answered by sneharani8789t
5

Answer:

45 days

Step-by-step explanation:

64 workers complete the work within=40×72/64=45 days answer.