10 labourers can repair a road in 15 days. In how many days can 30 labourers repair it?

Full solution..

Answers

Answered by ThatTechNerd
20
Let the no. of labourers who can repair the road be x

10/x = 15/30
x = 15*10/30
x = 5
Answered by darshanks911
15

Answer: shall we should follow inverse proportion so

10:30:15:x

15×10/30= 5

5 days needed needed for finishing for finishing work


Step-by-step explanation: