. 10 labourers take 8 days to complete a given job. How many days will 16 labourers take to complete the same job?
Answers
Answered by
4
Answer:
5
Step-by-step explanation:
Number of labour = 10
Complete a given job =8 days
So, 10×8 = 80/16 = 5 (By Dividing 80 and 16 comes 5)
5 days will 16 labourers take to complete same job