. 10 labourers take 8 days to complete a given job. How many days will 16 labourers take to complete the same job?
Answers
Answered by
0
Answer:
The election commission is
Answered by
0
Answer:
10 labourers complete a work in 8 days
1 labours complete the same work in 8×10 days
16 labour complete the work in 8×10/16 days
=5 days