10 labourers take 8days to complete a given job how many days will 16 labourers take to complete the same job
Answers
Answered by
3
Answer:
5 days
Step-by-step explanation:
m1*d1*h1=m2*d2*h2
m= men
d= days
h= hours
10*8 =16*x
x= 5
Answered by
0
Answer:2 days
Step-by-step explanation:
16 divide by 8 equals to 2