Math, asked by manikanta06, 7 months ago

10 machines do 50 jobs in 25 days. Find the
number of more machines required to complete
90 jobs in 15 days.​

Answers

Answered by ajayabhi
0

Answer:

10 machines do 50 jobs in 25 days.

1 machines do 5 jobs 5/1.

15 machine in 90= 5/1 ×15 solve this and find answer