10. Mason A can build a shed in 12 hours. Mason B takes
9 hours while Mason C takes 12 hours to do the same
job. If the three masons are put to work together how
long will they take to build the shed? How will the
payment of 1000 for the job be distributed amer
the three?​

Answers

Answered by bhaskarmaniraj95
2

Answer:

together: 36/10 =3.6 Hours.

300+400+300 = 1000

Answered by bidyananda334
0

Answer:

3 hours or 36 minute answer