10 masons can build a wall working 7 hours a day, in 12 days. In how many days can the work be completed by 14 persons working 8 hours a day?
Answers
Answered by
4
the time taken by 10 masons =84 hours
so the time taken by 14= 84*10/14 hours
or 5/2days
so the time taken by 14= 84*10/14 hours
or 5/2days