10 Masons can build a wall working 7 hours a day, in 12 days. In how many days can the work be completed by 14 persons working 8 hours a day?
Answers
Answered by
30
Total work done by 10 persons in 7 hour / day in 12 days = 12×7×10=840
Total work done by 10 persons = Total work done by 14 persons.
:. Total work done by 14 persons= 840
.'.Let the days required to complete the wall by 14 persons working 8 hours / day be X.
.'. Total work done by 14 persons working 8 hours/day=14×8×X= 112X
840=112X
X=840÷112= 7.5 days
.'. 7.5 days required to complete wall by 14 persons working 8 hours/day.
Hope helped
Total work done by 10 persons = Total work done by 14 persons.
:. Total work done by 14 persons= 840
.'.Let the days required to complete the wall by 14 persons working 8 hours / day be X.
.'. Total work done by 14 persons working 8 hours/day=14×8×X= 112X
840=112X
X=840÷112= 7.5 days
.'. 7.5 days required to complete wall by 14 persons working 8 hours/day.
Hope helped
kai123:
yes the answer is right
Answered by
15
Answer:
Step-by-step explanation:
10 masons can build a wall working 7 hrs a day in 12 days.
7 hr * 12 days = 84 hours
10*84 = 840 man-hrs to build the wall
----
14 men * 8 hr = 112 man-hrs/day
840/112 = 7.5 days