• 10 masons can build a wall working 7 hours a day, in 12 days. In how many days can the work be
completed by 14 persons working 8 hours a day?
Answers
Answered by
2
Answer:
A common sense way of solving this problem is
to first find the total number of hours taken by
10 masons working for 7 hours a day for 12 days
to build the wall.
= 10 masons x 7 hours/day x 12 days = 840
hours (total time taken to build the wall)
Now, assume that the number of days required
to build the wall by 14 masons working 8 hours
a day be y.
Using same common sense approach as
above, we get
14 masons x 8 hours/day x y = 840
.'. 112 x y = 840
%3D
.'. y = 840 ÷ 112 = 7.5 days
%3D