10 masons can build a wall working 7 hours a day in 12 days, in how many days can the work be completed by 14 persons working 8 hours a day?
Answers
Answered by
93
A common sense way of solving this problem is to first find the total number of hours taken by 10 masons working for 7 hours a day for 12 days to build the wall.
= 10 masons x 7 hours/day x 12 days = 840 hours (total time taken to build the wall)
Now, assume that the number of days required to build the wall by 14 masons working 8 hours a day be y.
Using the same common sense approach as above, we get
14 masons x 8 hours/day x y = 840
∴ 112 x y = 840
∴ y = 840 ÷ 112 = 7.5 days
= 10 masons x 7 hours/day x 12 days = 840 hours (total time taken to build the wall)
Now, assume that the number of days required to build the wall by 14 masons working 8 hours a day be y.
Using the same common sense approach as above, we get
14 masons x 8 hours/day x y = 840
∴ 112 x y = 840
∴ y = 840 ÷ 112 = 7.5 days
Answered by
17
Answer:
7.5 days
Step-by-step explanation:
A common sense way of solving this problem is to first find the total number of hours taken by 10 masons working for 7 hours a day for 12 days to build the wall.
= 10 masons x 7 hours/day x 12 days = 840 hours (total time taken to build the wall)
Now, assume that the number of days required to build the wall by 14 masons working 8 hours a day be y.
Using the same common sense approach as above, we get
14 masons x 8 hours/day x y = 840
∴ 112 x y = 840
∴ y = 840 ÷ 112 = 7.5 days