Math, asked by TriviaTramp, 8 months ago

10 mean build a wall in 5 days then 15 men will build a wall in how many days?
Please answer this question fast. And tell if it is Direct or Inverse Variation.

Answers

Answered by ompathak60
2

Answer:

5/10* 15= 7.5 days . if correct mark as branliest

Answered by Anonymous
4

It's Inverse Variation...

10 men completes the work in → 5days

1 man can complete the work in → 5×10=50days

so,

15men can complete the work in → \frac{50}{15} = \frac{10}{3} days