10 men can complete a work in 18 days. After 6 days, five more men are employed. In how many days will the remaining work be completed?
Who will answer I will mark him brainliest
Answers
Answered by
2
Step-by-step explanation:
That’s the answer, 8 days remaining.
Answered by
1
Answer:
9 days
Step-by-step explanation:
Time taten by 10 men to complete a task = 18 days
10x = 18 days
so......
10x + 5x = ? days
15x = 9 days as more the men less time taken to finish a work.