10 men can construct a wall of 180m long in 3 days how many men are required to construct 300m ling wall in 5 days

Answers

Answered by graxx
6
Hi there

10 men took 3 days to construct 180.m long wall

then im 1 day ..they constructed 60m long wall (eq 1)


So For 300 m long wall.

300 ÷ 5 = 60


So It is required that in one day they should construct 60 m long wall.

It means That 10 men are required . *(From eq 1)


10 men ( ans )


Thank You