10 men can dig a trench in 15 days .How longer can 3 men
Answers
Answered by
0
Answer:
please MARK as the BRAINLIEST and become my follower
Attachments:
Answered by
0
Answer:
10 men take 15 days
now we have find for 3 men..
As the men decreased so the time will increase
so time and men is inversely proportional..
so
(10×15)/3 days
=150/3 days
=50 days
Step-by-step explanation:
mark as brainliest if it helps.