10 men can finish a piece of work in 10 days. Whereas it takes 12 women to finish it in 10 days if 15 men and 6 women undertake to complete the work. How many days will they take to complete it?Select one:a. 2b. 11c. 4d. 5
Answers
Answered by
0
Step-by-step explanation:
10 men = 12 women
15 men = (12/10)*15
= 18 women
15men+6woman= (18+6) woman
= 24 woman
12 women can finish a work in 10 days
1 woman can finish that work in 12*10days
24 women can finish that work in 120/24 days
= 5days