10 men can finish painting a wall in 12 hours. How many more men are required if the work is to be done in 8 hours?

Answers

Answered by bagkakali
0

12 hours required for 10 men

1 hour required for 10×12 men

8 hours required for 10×12/8 men=15 men

then(15-10)=5 more men requared