10 men can finish the construction of a wall in 8 days.How many men are added to finish the work in half a day?
Answers
Answered by
3
Answer:
The Answer is 150
Step-by-step explanation:
Let x men are added to finish the work in half day
Since, 10 men can finish the construction of the wall in 8 days.
Men can finish the construction of a wall in 1 day.
So, 10 × 8 = 80
Men can finish the construction of a wall in 1/2 day.
80 × 2 = 160
Hence,
160 - 10 = 150 men are added to finish the work in half day.