10 men can prepare 20 toys in 3 days working 12 hours a day. In how many days will 24 men prepare 32 toys working 4 hours a day?

Answers

Answered by amitnrw
47

Answer:

6 Days

Please mark as brainliest if u liked

Step-by-step explanation:

10 Men * 3 days * 12 hr = 360 man hrs for  20 toys

20 toys  required  360 man hrs

1 toy required = 360/20

32 toys required = 18*32

Days require by 24 men working 4 hrs a day = 18*32/(24*4)

= 6 Days