10 men complete a work is 4 days. How many days would 8 men take?​

Answers

Answered by anne1njenga2
0

Answer:

5men

Step-by-step explanation:

10men=4days

8men

10×4÷8=5men

Answered by jprithvi2006
0

Answer:

Number of men. No of days

10 4

8 x

More the men lesser the number of days required to finish the work.

So, the number of men and the number of days required to complete the work are inversely proportional to each other.

10/8=x/4

⇒ x =10×4/8

⇒ x=5

Thus, when 8 men are involved so, 5 days will be required.