Math, asked by rakeshkumar4586, 10 months ago

10 men complete any work in 8 days and 16 women complete same work in 10 days. 8 women start the work and stop working after 4 days. How many men will complete the remaining work in 4 days?

Answers

Answered by Pitymys
1

Answer:

16 men

Step-by-step explanation:

According to the question,

10m × 8 = 16w × 10

1m = 2w

8 women = 4 men

Let x men complete the remaining work in 4 days.

10 × 8 = (4 × 4) + (4 × x)

80 = 16 + 4x

4x = 64

x = 16 men

if you like my answewer please support by giving thanks