Math, asked by Ssaha456, 8 months ago

10 men or 18 women can do a piece of work in 38 days in how many days will 6 men and 12 women do it together​

Answers

Answered by kanishkjoshi3
0

6 men can complete work in 63 days

and 12 women can complete work in 57 days

Step-by-step explanation:

10 men complete whole work in 38 days l

so 1 man =10*38

so 6 men =10*38/6=63.33days .

18 women complete same workin 38 days

so 1 women=18*38

so 12 women 18*38/12=57days

Similar questions